What is the term for a checklist of required repairs and discussions with the customer at the job's conclusion?

  1. Quality assurance list

  2. Final punch list

  3. Completion checklist

  4. Customer approval list

The correct answer is: Final punch list

The term "Final punch list" refers to a detailed checklist created at the end of a construction project or job, which outlines any remaining tasks or repairs that need to be addressed before the project can be considered complete. This list is typically presented to both the contractor and the customer so that there is a clear understanding of what outstanding work needs to be done. Creating a final punch list is an essential step in ensuring customer satisfaction, as it ensures that the expectations set at the beginning of the project are met and that any final adjustments are documented and agreed upon. This process allows the contractor to formally close the project while allowing the customer to verify all necessary repairs or touch-ups before final payment is made. In contrast, the other options might sound relevant but do not accurately capture the specific purpose and timing associated with a punch list. For example, quality assurance lists focus on the overall quality of the work rather than specific tasks to be completed, and customer approval lists may not necessarily include the detailed breakdown of repairs at project closeout that a punch list does. Similarly, a completion checklist may cover various aspects of project completion but lacks the specificity and focus on repairs that characterizes a final punch list.