A claim of lien must be filed within how many days after being on the job site?

  1. 60 days

  2. 90 days

  3. 120 days

  4. 30 days

The correct answer is: 90 days

In Michigan, a claim of lien must be filed within 90 days of the last day of work performed on the job site. This is an important legal requirement for contractors and suppliers who wish to secure their right to payment for work completed. The 90-day period is specifically designed to provide a balance between the rights of the property owner and the right of the contractor or supplier to claim payment. This timeframe ensures that contractors have a reasonable opportunity to assert their claims while also allowing property owners to be aware of any potential liens in a timely manner. If a contractor fails to file a lien within this period, they may lose their right to recover the debt through a lien against the property, which is a significant aspect of construction law in Michigan. Understanding this timeline is crucial for anyone in the construction industry in Michigan, as it impacts cash flow and financial planning for projects. Knowing the correct period helps ensure that contractors protect their rights effectively while also complying with state regulations.